Yhteystiedot
Katso oman alueesi NKT:n yhteyshenkilöt tästä.
Three windmills at sea

Kriegers Flak, The Baltic Sea, Denmark

NKT supplies transmission links to, from and between wind farms and national energy grids.

Key facts - Grid connection // Combined grid solution

Principal

Energinet // 50Hertz and Energinet

Location of the project

The Baltic Sea, Denmark // The Baltic Sea, Germany and Denmark

Quality of order

A turnkey 220 kV HVAC cable system with a 600 MW power rating // A turnkey 170 kV high-voltage cable system with a 400 MW power rating

Total cable length

100 km // 50 km (two parallel cable systems of 25 km)

Duration

2015-2019 // 2017-2019

Cable systems for renewable energy integration

Connecting offshore wind farms to onshore grids is essential to enable integration of more renewable energy and pave the way for a sustainable future. In turn, interconnecting grids create opportunities to strengthen energy markets, secure supply and share capacity. As the selected supplier of cable systems and installation work, NKT contributes to the unique Kriegers Flak development in the Baltic Sea. Two national electricity grids are being connected via offshore wind farms. The European power transmission system is evolving towards an infrastructure based on high-voltage cable systems. The Kriegers Flak connection and interconnection showcase this transformation and support the European Union’s goal of reaching a minimum of 27 percent renewable energy by 2030.
High voltage cable production at NKT facility in Cologne
Three windmills at sea

Kriegers Flak grid connection

Denmark’s largest offshore wind farm, Kriegers Flak, is connected to shore by NKT.

NKT’s solution consists of 220 kV (kilovolt) HVAC (high-voltage alternating current) cable systems between the offshore transformer platforms as well as connections to shore. The advanced solution enables the integration of 600 MW (megawatt) into the mainland grid, and brings green energy to 600,000 Danish households. Design, testing and production of the submarine cable system were conducted in NKT’s world-class facilities in Karlskrona, Sweden. NKT was also responsible for installation, cable-laying and pull-in operations for the three-core submarine cables. This approach significantly reduces interface risk thanks to NKT’s in-depth understanding of both cable systems and installation methodology. NKT’s experience and expertise ensure reliable transmission of electrical energy. The offshore cable laying, platform connection and land installation was successfully performed with the state-of-the-art cable laying vessel NKT Victoria. The vessel is built specifically for the task of handling and laying submarine cables. The performance was excellent, with regards to both speed and accuracy, and the mission was completed within the scheduled time. This grid connection has a total length of about 100 km, of which 11 km is between platforms and 44 km is from each of these platforms to shore, the project was massive and called for smooth execution. As a supplier of the cable system and installation, NKT provided its expertise throughout the value chain, which enables a safer and more predictable project execution, both in terms of liabilities and costs. The cable system will finally be taken into service in 2019.
Reference map for Krieger's Flak project

Kriegers Flak Combined Grid Solution

NKT is securing green power transmission between Germany and Denmark.

Transmission system operators 50Hertz of Germany and Energinet of Denmark have established the world’s first offshore interconnection by using the national grid connections to the offshore wind farms Kriegers Flak and Baltic 2. The Kriegers Flak combined grid solution uses a submarine cable system from NKT. It has been designed and manufactured at our optimized factory in Cologne,Germany. The interconnection contributes to a high level of secure supply of electric power. It also allows producers and consumers to buy and sell more power across the borders, increasing the value of renewable energy and contributing to the green transition. As the grids are a synchronous, a frequency transformation is necessary. An offshore transformer has been placed on an additional offshore platform due to the different voltage levels of the Danish and German offshore wind farms. The Kriegers Flak combined Grid Solution holds the status of a “project of common interest”, given by the European Commission. Such projects are grid expansions of significant importance, as they bridge gaps in the infrastructure of the European power system and simplify the development of a common European energy market. At NKT, we are proud having participated and having used our extensive experience and knowledge to support this important project, which has been commissioned in April 2019.

Our cable system is part of the world’s first offshore power grid that combines wind energy with the possibility to exchange power between two countries.

— Claes Westerlind, Head of HV Solutions Karlskrona

News

NKT completes important milestone

Power cable systems from NKT are at the heart of Kriegers Flak Combined Grid Solution which is the world’s first offshore interconnector using the national grid connections of offshore wind farms to connect the power grids of Denmark and Germany.
Read more
Three windmills at sea

NKT Uutiskirje

Haluatko pysyä ajan tasalla? Tilaa uutiskirjeemme saadaksesi säännöllisiä uutisia trendeistä, tuotteista ja tapahtumista.

Seuraa meitä

Oikeudenmukainen, kestävä - ja vastuullinen
  • Image of europacable logo
  • Image of ecovadis logo
  • Image of Endorser Logo
  • 01_Copper Mark_logo_RGB_Primary.png
Loading...